Budhi Gandaki,
Nepal

A two-stage cascade on the Budhi Gandaki River in Gorkha District, about 140 km by road from Kathmandu. Both stages hold generation licenses and signed PPAs.

Budhi Gandaki riverbed at the KHA dam site, Gorkha
Budhi Gandaki riverbed · KHA dam site, Gorkha · 28.2°N 84.6°E
Contracted under PPA · 390 MW licensed
329.4MW
Average annual generation
1,828GWh
Of output in the dry season
>30%
PPAs signed for both projects
Take-or-pay

Three features stand out: high utilization, a large share of dry-season output and long-term take-or-pay PPAs.

  • 5,400+ hours

    Design utilization of 5,592 hours (KHA) and 5,454 hours (KA), higher than any plant in our current fleet.

  • Dry-season generation

    Daily regulation lets both plants concentrate output in peak hours, and by design more than 30% of their annual energy comes in the dry months.

  • Long-term PPAs

    Take-or-pay power purchase agreements signed with the Nepal Electricity Authority in April 2024, running 30 years from commercial operation.

Project locations · Nepal
80°E81°E82°E83°E84°E85°E86°E87°E88°E30°N29°N28°N27°NBUDHI GANDAKI KA + KHAGorkha · 329.4 MW hydroKathmandu
  • BUDHI GANDAKI KA + KHAGorkha · 329.4 MW hydro

Technical profile

Technical profile of the Budhi Gandaki KHA and KA projects
BUDHI GANDAKI KHA226 MWBUDHI GANDAKI KA103.4 MW
Cascade positionDownstreamUpstream
Licensed capacity260 MW130 MW
Of which under take-or-pay PPA226 MW103.4 MW
LocationGorkha, Gandaki ProvinceGorkha, Gandaki Province
Units3 × 75.3 MW Francis2 × 51.7 MW Francis
Dam typeConcrete gravityConcrete gravity
Dam height × crest length37 m × 282 m50 m × 130.5 m
RegulationDaily · pondage for ≥ 5.5 h of peakingDaily · pondage for ≥ 5 h of peaking
Headrace tunnel8.49 km3.72 km
Design discharge135 m³/s134 m³/s
Rated head195 m89 m
Average annual generation (PPA)1,264 GWh564 GWh
Annual utilization5,592 h5,454 h
Dry-season share of output> 30%> 30%
Offtaker · termNEA · 30 years from CODNEA · 30 years from COD

Licensed and PPA capacities are contractual. Generation, utilization, dam dimensions and target dates are from the feasibility study, which is being finalized, and may change.

Where the projects stand today.

  1. Completed:

    EIA approval

    Both projects

  2. Completed:

    Grid connection agreement

    Signed; 220 kV transmission route approved 2025

  3. Completed:

    Generation licenses

    KHA 260 MW · KA 130 MW

  4. Completed:

    PPAs signed

    With NEA · 329.4 MW take-or-pay

  5. Completed:  

    Design institute

    PowerChina Kunming Engineering Corporation

  6. Target:

    Feasibility study completion

    Target · KHA Nov 2026, KA May 2027

  7. Target:

    Construction start

    Target · EPC tender Jan 2027

  8. Target: Date TBA

    Commercial operation

    KHA and KA

Targets as of October 2026.

Managing environmental and social impact

  • Impact assessment

    Environmental impact assessments approved in 2013.

  • Land and resettlement

    Project land is predominantly state-owned; land acquisition and limited resettlement are under way.